Message: | Albion is from Turkey, and has cooperated with AAK on hydraulic manifold blocks for 2 years. In the second half of last year, they received a sample order for hydraulic manifold blocks, and the customer requested to deliver the samples within 60 days. For hydraulic valve standard parts, this time frame is OK. However, for the customized hydraulic manifold block, it is some difficult to finish in 45-50 days. Albion contacted a local hydraulic manifold block manufacturer, but after receiving the drawings, the manufacturer said it was too late. Because this hydraulic manifold block has a high degree of integration, many types of cavity holes, multiple machine tool positioning, complex processing, and the need for customized molding tools, it needs at least 60 days. Albion has contacted more than 10 hydraulic manifold block manufacturers, none of them can catch the schedule. Albion was worried. |